Construction timeline documents and blueprints on a table with Park City home under construction visible through window
Back to Blog
Process & PlanningFebruary 202510 min read

Custom Home Build Timeline in Park City — What to Expect

"How long will it take?" is the second question every client asks (right after "how much will it cost?"). The honest answer for a custom home in the Park City area: 14–24 months from first conversation to move-in, with most projects landing in the 16–20 month range. Here's a realistic breakdown of where that time goes — and the delays most builders won't tell you about until you're already committed.

The Full Timeline: Month by Month

We break the custom home timeline into four major phases. Each has its own variables, but together they form the complete picture from "I want to build" to "I'm moving in."

Phase 1

Preconstruction Planning — Months 1–4

This is where most of the critical decisions happen — and where most builders rush through or skip entirely. At Three Peak, our paid planning phase covers:

Month 1

Initial consultation, site visit, lot analysis, geotechnical investigation ordered, architect selection/engagement, preliminary budget discussion

Month 2

Schematic design development, geotechnical report received, preliminary engineering, soil ordinance compliance planning, HOA/DRC pre-submission meeting (if applicable)

Month 3

Design development, material selections begin, detailed cost estimating with trade partners, structural engineering, MEP design coordination

Month 4

Construction documents finalized, final budget presentation (low/likely/high), permit application submitted, DRC submission (if applicable), construction contract execution

Note: If building in a design-reviewed community like Deer Valley, add 2–4 months for the architectural review process.

Phase 2

Site Work & Foundation — Months 5–7

Once permits are in hand, construction begins with the most weather-dependent and site-specific work:

Month 5

Site mobilization, erosion control installation, tree protection, excavation begins, utility trenching, retaining walls (if needed)

Month 6

Foundation forming and pouring, waterproofing, backfill, underslab plumbing and electrical rough-in, garage slab

Month 7

Foundation curing, framing lumber delivery, subfloor installation, framing begins on lower level

Critical variable: Rock excavation can add 2–4 weeks and $50,000–$200,000+ to this phase. This is why the geotechnical report during preconstruction is non-negotiable.

Phase 3

Framing Through Dry-In — Months 7–11

This is the most visible phase — the house takes shape rapidly. But it's also where coordination between trades becomes critical:

Months 7–9

Structural framing (walls, floors, roof), steel beam installation, sheathing, window and door rough openings, deck framing

Month 9–10

Roofing installation, window and door installation, exterior weather barrier (house wrap/fluid-applied), exterior stone and siding begins

Month 10–11

Mechanical rough-in (HVAC ductwork, radiant tubing), electrical rough-in, plumbing rough-in, insulation, drywall begins

The goal is to be "dried in" (roof on, windows in, weather-tight) before the first heavy snow. If you miss this window, exterior work pauses until spring.

Phase 4

Finishes & Completion — Months 11–16

The finish phase is where the home transforms from a construction site into a living space. It's also the phase most prone to delays from material lead times and change orders:

Months 11–12

Drywall finishing, interior painting, cabinetry installation, tile work begins, hardwood flooring acclimation

Months 12–14

Countertop fabrication and install, plumbing fixtures, electrical trim (switches, outlets, fixtures), appliance installation, millwork and trim carpentry

Months 14–15

Hardwood flooring installation and finishing, final paint touch-ups, hardware installation, closet systems, glass shower enclosures

Month 15–16

Final mechanical commissioning, landscaping and hardscaping, driveway and snow-melt activation, punch list, final inspections, certificate of occupancy

The Delays Most Builders Won't Tell You About

Every custom home project encounters delays. The difference between a well-managed project and a nightmare is whether those delays were anticipated and planned for. Here are the most common timeline killers in the Park City area:

Winter Weather Shutdowns

4–12 weeks

Foundation and exterior work is extremely difficult from November through March at 7,000+ feet. If your project isn't dried-in before first snow, expect a 3–4 month pause on exterior work.

Permit Processing

4–8 weeks

Park City and Wasatch County permit offices are understaffed relative to demand. Plan for 6–8 weeks for permit review, longer during peak building season (spring applications).

Material Lead Times

4–16 weeks

Custom windows (Marvin, Loewen): 12–16 weeks. Custom cabinetry: 8–12 weeks. Natural stone: 6–10 weeks. Steel beams: 4–8 weeks. These must be ordered months before they're needed on site.

Subcontractor Availability

2–6 weeks

Summit County has a limited pool of qualified trades. During peak season (May–October), the best electricians, plumbers, and HVAC contractors are booked 4–6 weeks out.

Design Changes During Construction

2–8 weeks per change

Every mid-construction change requires re-engineering, re-pricing, re-scheduling, and often re-permitting. The single biggest cause of timeline overruns.

Inspection Scheduling

1–3 weeks per inspection

Required inspections (foundation, framing, mechanical, insulation, final) must be scheduled with the county. During busy periods, inspectors may be booked 1–2 weeks out.

How to Protect Your Timeline

The projects that finish on time share common characteristics. Here's what we do at Three Peak to protect the schedule:

  1. 1.
    Complete all design decisions before breaking ground

    Our preconstruction phase requires that every material, fixture, and finish is selected and ordered before construction begins. No "we'll figure it out later" on critical-path items.

  2. 2.
    Order long-lead materials immediately after contract signing

    Windows, steel, custom cabinetry, and specialty stone are ordered 4–6 months before they're needed on site. This eliminates the most common material delay.

  3. 3.
    Build weather contingency into the schedule

    We assume 4–6 weeks of weather delays for any project that spans a winter season. If we get lucky with weather, we finish early. If we don't, we're still on schedule.

  4. 4.
    Lock in subcontractor schedules early

    We confirm trade schedules 6–8 weeks in advance and maintain relationships with backup crews for critical-path trades.

  5. 5.
    Minimize change orders

    The thorough preconstruction process means fewer surprises and fewer mid-build changes. When changes do happen, we assess timeline impact immediately and communicate it clearly.

When to Start If You Want to Move In By a Specific Date

Working backward from common move-in targets:

Move in by ski season (December)Begin preconstruction by June–August of the previous year
Move in by summer (June)Begin preconstruction by December–February of the previous year
Move in by fall (September)Begin preconstruction by March–May of the previous year

The best time to start planning is 18–24 months before your desired move-in date. The second-best time is now. Learn more about how our process works and what the first steps look like.

The Bottom Line

A custom home in Park City takes 14–24 months from first conversation to move-in. The single biggest factor in whether you land on the shorter or longer end of that range is the quality of preconstruction planning. Projects that rush into construction without completing design, ordering materials, and resolving site challenges inevitably take longer and cost more. Projects that invest in thorough planning upfront finish on schedule because the surprises have already been identified and solved on paper.

Next Step

Ready to start the clock?

The sooner we start planning, the sooner you're in your new home. Schedule a complimentary walk-through and we'll map out a realistic timeline for your specific project.

Schedule a Consultation

Timeline expectations vary by jurisdiction. Learn more about building in Park City and across Summit County. View all service areas.